Banks Co. Bridge Under Construction

If you’re headed to Banks County, be aware of some bridge construction now underway on SR323.

Georgia Department of Transportation crews are replacing the 65-year-old bridge over Grove Creek. 

Crews with the Georgia DOT’s contractor, Talley Construction Company, Inc. of Rossville, GA are installing construction related traffic signs and orange barrier fence along the borders of the project.

Replacing the 28-foot bridge will be a 37.25-foot bridge north of the current bridge. This was done to minimize the environmental impacts in the area of Grove Creek. 

The current bridge will remain open to traffic until traffic is switched to the new bridge, then demolished.

This project was awarded in Sept. 2016 and is scheduled to be completed April 2019.